City of Cameron issued the following announcement on June 12.
Project is Wholly Funded by the Clean Water State Revolving Fund (CWSRF) thru
the Texas Water Development Board (TWDB)
Description of Project:
- Replacement or Rehabilitation of Eight (8) existing lift stations within the City of Cameron including replacement of all pumps, discharge piping, valves, electrical panels and appurtenances at each site.
- Furnish and Install six (6) new concrete valve vaults with new 4”/6” ductile iron piping, gate valves, check valves, air and vacuum combination valves and additional appurtenances.
- Rehabilitate two (2) existing valve vaults to replace gate valves, check valves and installation of new air and vacuum combination valve.
- Sawcut Existing Roadways or Driveways where necessary to allow for Wet Well or Valve Vault installation.